Nathan Benderson Park Southern Shoreline Stablization
Post Date:06/03/2026 10:30 AM
Project Description
The shoreline of the large rowing lake at Nathan Benderson Park has experienced erosion from excessive wave activity caused by multiple powerful storms and hurricanes.
Initial southern shoreline stabilization efforts began in the fall of 2022. Soon after demolition activities were completed, the park was impacted by Hurricane Ian. Restoration work for the floating docks and shoreline near the southwest corner of the lake was completed in 2023 and 2024. However, the extensive damage to the center and southeast section of the shoreline required additional engineering design and permitting efforts.
The park will remain open during construction. There may be temporary, partial closures of the lake perimeter trail to accommodate restoration activities.
In the early 1990s, the site was an active shell excavation pit used for road construction. Sarasota County purchased the land and initially named it Cooper Creek Park.
A New Vision:
In 2007, the park was renamed after Nathan Benderson, the founder of Benderson Development, following a $1 million donation from the Benderson family to transform the area into a health and wellness destination.
World-Class Infrastructure:
The park features the only permanent FISA Class A 2,000-meter sprint rowing course in North America. Significant infrastructure upgrades include a five-story finish tower completed in 2017.
Economic & Community Impact:
NBP hosted the 2017 World Rowing Championships, which generated nearly $20 million in economic impact for the Sarasota-Manatee area.
Versatile Usage:
Beyond professional rowing, the park serves as a hub for dragon boat racing, triathlons, 5k/10k runs, and public recreation like kayaking, biking, and picnicking.
Shoreline stabilization work is progressing along the east side of the lake, where crews are installing geotextile fabric and riprap to protect against erosion. Construction is moving steadily from north to south toward the lake’s southeast corner. The new boat ramp is also beginning to take shape, with recently installed sheet piling outlining its future footprint.
April 30, 2026
Construction is currently underway along the east and southern shoreline of the lake. Crews are re‑establishing shoreline slopes and stabilizing them using geotextile fabric and riprap.
Along the east shoreline, repair work has begun approximately 1,500 feet north of the lake’s southeast corner, progressing from north to south.
Near the boat ramp, the shoreline slopes have already been rebuilt, and installation of geotextile fabric and riprap is ongoing. The damaged boat ramp has been removed, and a coffer dam is now in place to support construction of the new ramp.
March 31, 2026
The notice to proceed for construction activities along the southern and southeastern shoreline was issued on March 24, 2026. Contractors have mobilized onsite and will soon be installing protective measures at the project work areas. Work is anticipated to be completed in early fall 2026.