Project Description
|
This project is for the design and construction of a pedestrian sidewalk parallel to the Legacy Trail Extension. The sidewalk will allow pedestrians and cycles separate pathways in selected areas of the Trail. The sidewalk will be asphalt, 6-feet wide with a a sod strip separating it from the main trail. The Project will be fully designed and then built in phases. Phase 1 will stretch from Shade Avenue to Beneva Road, about 1.4 miles in length and is scheduled to start construction in October 2025.

Sarasota County Projects in My Neighborhood
|
|
|
|
Funded by:
North County Park Impact Fees
Recreational Trails Program Grant
Private Donation
|
Design by:
Kimley-Horn and Associates, Inc.
|
Contractors:
Spectrum Underground, LLC
|
Updates:
April 30, 2026
Ribbon cutting ceremony was held on March 31, 2026.
The project construction is complete.
March 31, 2026
The ribbon‑cutting ceremony for the Legacy Trail Extension Bifurcated Trail was held on March 31, 2026. Commissioners Ron Cutsinger, Mark Smith, Teresa Mast, and Dr. Joe Neunder attended the event, along with representatives from design contractor Kimley-Horn, construction contractor Spectrum Underground, the County Administrator Jonathan Lewis, ACA Nicole Rissler, Interim Director Shawn Yeager, county staff, and community guests.
This new 1.5‑mile segment features a six‑foot‑wide pedestrian sidewalk running parallel to the Legacy Trail Extension, offering designated spaces for pedestrians and cyclists in select areas to enhance safety and user experience. The project was made possible through generous support from the Friends of the Legacy Trail, a grant from the Florida Department of Environmental Protection’s Recreational Trails Program, and North County Park Impact Fees.
The trail is now officially open and ready for everyone to enjoy!





You are invited!

February 28, 2026
A substantial completion walk-through was held on February 18, 2026. Minor punch‑list items are currently being finalized. The project is on track to celebrate its opening with a ribbon‑cutting ceremony on March 31, 2026.



January 31, 2025
Paving of the bifurcated trail is now complete from Beneva Road to Tuttle Avenue. From Tuttle Avenue west to Shade Avenue, the base material has been installed, and paving will begin soon.


December 31, 2025
The old sod has been removed, and a strong subbase has been installed to prepare for the next step. Asphalt paving is scheduled for the week of January 5, 2026, bringing us closer to a more accessible pathways for everyone to enjoy.


November 30, 2025
Progress continues on the first section of the bifurcated trail. Crews have been hard at work clearing most of the existing sod to prepare the area for the next phase: base installation. This important step lays the foundation for a smooth and durable trail surface, bringing us closer to a completed path that will soon be ready for public use.



October 31, 2025
Sarasota County received the official Notice to Proceed (NTP) from the Florida Department of Environmental Protection (FDEP) on October 16, 2025. This marked a key milestone, authorizing the start of construction activities under the terms of the grant agreement. The 120-day contract period officially began on October 20, 2025, as outlined in the FDEP agreement.
Following this, the County issued its formal Construction Notice to Proceed on October 27, 2025, after receiving the required documentation from the contractor. This notice allows full mobilization and the start of on-site work.
The first visible activity began shortly after: survey staking started on October 29, 2025, which is a critical step in marking out the exact locations for construction based on the approved site plans.
We appreciate the community’s continued support and patience as we move forward with this exciting project. These early steps lay the foundation for the improvements to come, and we look forward to sharing more updates as construction progresses.
September 30, 2025
This project involves the design and phased construction of a new pedestrian sidewalk running parallel to the Legacy Trail Extension. The goal is to enhance safety and accessibility by providing a dedicated asphalt pathway for pedestrians, separate from the main trail used by cyclists.