Park Projects

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Below are select Parks, Recreation and Natural Resources' Capital Improvement Projects and other projects that are currently in progress.

Learn more about these and other Projects In Your Neighborhood.

 

Twin Lakes Park Pickleball Improvements

Post Date:06/03/2026 8:00 AM

Project Description


The proposed improvement project includes the construction of six lighted pickleball courts, fencing, shade structure, accessible pedestrian connections, and associated amenities. This project also includes potential lighting for the existing tennis courts.

 

 5883 Hummingbird Avenue

 TLP_Pickleba CONCEPT (

 

Funded by:
South County Park Impact Fees,

North County Park Impact  Fees

 

Design by:

George F Young Inc.

299 Dr. Martin Luther King Jr. Street N

St. Petersburg, FL 33701

 

Contractors:

Jon F Swift Construction

2221 8th Street, Sarasota FL 

 

Updates:

You are invited!!! Please join us for the Ribbon Cutting!

PRNR Admin Building Ribbon Cutting eVite

May 31, 2026

June 1, 2026 — Improvements to the pickleball courts, as well as upgrades to the tennis and racquetball courts, are nearing completion. All fencing and the new shade structure have been installed. Six southern red cedar trees have been planted at the northeast corner of the pickleball courts, and the surrounding area has been freshly sodded. The asphalt is now being prepared for the court‑surfacing materials, and new site furnishings are arriving.

A combined ribbon‑cutting ceremony will take place on June 9 to celebrate the opening of the new Parks Administration Building, the Twin Lakes Park Community Building, and the new pickleball courts.

TLP.Bathroom.Building.5.28TLP.Pickleball.Interior.Shot.5.28

260528_TLPTLP.Tennis.Court.5.28

April 30, 2026

Progress continues on the courts. Lighting installation was completed on April 20, 2026, followed by site grading on April 23. Asphalt was placed for the tennis courts on April 24 and for the pickleball courts on April 27. Work on the perimeter concrete curbs and fencing will begin soon.

Estimated project completion: June 2026.

260422_TLP_Tennis_Court260422_TLP_Both_Courts

 

IMG_0573260422_TLP_Outdoor_Restrooms

March 31, 2026

Work is moving forward on the new pickleball courts. The court pad has been completed, drainage improvements are underway, and installation of the light poles is ongoing. The project is currently estimated to be completed in late May 2026.

TLP-Pickleball_Stormwater_install_260324TLP_Grading_Pickleball_Courts

TLP_Setting_Pickleball_light_260309

 

February 28, 2026

Demolition began on February 2, 2026. Musco light poles and fixtures are scheduled for delivery in early March, and the project is estimated to be completed by May 2026.

260225_TLP_Pickleball (3)260225_TLP_Pickleball (2)

260225_TLP_Pickleball (1)

 

January 31, 2026

Silt fencing and tree protection have been installed and inspected. Demolition is scheduled to begin on February 2, 2026. Court lighting poles and fixtures are expected to arrive in early February.

 

260114_TLP_Pickleball4260114_TLP_Pickleball3

TLP-Pickleball_011

December 31, 2025

Construction officially began with the issuance of the Notice to Proceed on December 15, 2025. Just a few days later, on December 19, 2025, the project team held a pre-construction meeting to finalize plans and ensure everything was ready for a smooth start.

November 30, 2025

We’re excited to share that the construction contract for the new pickleball courts was officially approved by the Board of County Commissioners on November 18, 2025.  Construction is expected to begin in early December, with crews preparing to break ground soon. Stay tuned for updates as we move forward.

 

October 31, 2025

The construction contract is currently being finalized and is scheduled to be presented to the Board of County Commissioners for approval on November 18, 2025. This is a critical milestone that will officially authorize the next phase of construction and allow work to proceed on schedule.

In preparation for future site enhancements, Musco court lighting—a high-performance lighting system known for its quality and energy efficiency—has already been ordered. These lights will provide professional-grade illumination for the courts, ensuring a safe and enjoyable experience for users during both day and evening hours.

We’re excited to see the project advancing and remain committed to keeping the community informed every step of the way. Stay tuned for more updates as we move closer to breaking ground!

September 30, 2025

We’re excited to share that the Site Development Permit has been officially approved by Sarasota County—marking a major step forward in bringing this project to life.

The construction contract is currently in progress and is expected to be finalized by November, allowing us to move into the active build phase shortly thereafter.

In preparation for upcoming work, we are also coordinating a direct purchase of court lighting from Musco Lighting.  This early procurement helps streamline the construction timeline and ensures quality lighting for future recreational use.

August 31, 2025

The permit review process is actively moving forward—we’ve received comments from the permitting entities, carefully reviewed and addressed each one, and have now resubmitted the updated plans for final approval.  This step is a vital part of ensuring that every detail of the project meets the highest standards for safety, compliance, and quality.

As we await the green light, we’re continuing to push forward on all fronts, laying the groundwork for a space that will serve and inspire our community for years to come.

July 31, 2025

We've received the permit comments, addressed every detail, and have already resubmitted the revised plans for review. We're moving forward toward the next steps!

June 30, 2025

The project has reached 90% design plans and have submitted the plans for Site Development permit review. This significant progress brings us one step closer to making the vision a reality!

May 31, 2025

We are thrilled to announce that we have received 90% of the construction documents! Our team is meticulously reviewing them before we submit for permits. Stay tuned for more updates as we move closer to breaking ground!

April 30, 2025

Project engineer is working to address plan review comments.

March 31, 2025

The 90% plans have been meticulously reviewed, and our dedicated engineer is now passionately working on the exciting revisions to bring this project to the next level!

February 28, 2025

The design phase is progressing brilliantly with 60% of the work received from George F Young Inc. and currently under review by County Staff.

January 31, 2025

Exciting news! Twin Lakes Park is getting a fantastic upgrade. Soon, you'll be able to enjoy six brand-new, lighted pickleball courts, adding even more fun to the park's already amazing amenities!

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Windows Media Player Download Word Viewer Download Excel Viewer Download PowerPoint Viewer